Case study / 01Grid supply & DNO

Surrey data centre campus

2026 · 11 kV · Acting directly for the client

Working directly for the client, we secured an additional uplift on a constrained network, taking the site from 23 to 27 MVA across its two 11 kV supplies, and coordinated the DNO works through to completion. On a second building, we raised a supply from 2.4 to 4 MVA, giving N-1 resilience that was not possible before.

Before23 MVA2 × 11.5 MVA
After27 MVA2 × 13.5 MVA
Voltage11 kVSupplies A and B
StatusCompleteDNO works, July 2026
ADDITIONAL UPLIFT · 23 → 27 MVAALL STAGES COMPLETE CAPACITYEstablishedFEB–MAR 2026APPLICATIONSubmittedMAR 2026OFFERReceivedAPR 2026ACCEPTANCESignedMAY 2026DNO WORKSCompletedJUL 2026AGREEMENTSCountersignedSEP 2026
From the first capacity check in February to signed connection agreements in September.
EXISTINGSECURED BY US 8.58.517 MVA11.511.523 MVAAB11.511.5+2+227 MVA EARLIERORIGINAL UPLIFTADDITIONAL UPLIFT BY OTHERSSECURED BY US
Combined import capacity across supplies A and B, in MVA. Solid black shows the uplift we secured.

What we did

  • Established what capacity was genuinely available to the site on a constrained network, and which allocation belonged to it.
  • Secured the additional uplift with the DNO: each 11 kV supply from 11.5 to 13.5 MVA.
  • Coordinated site meetings, access and the DNO works, through to signed connection agreements.
  • On a second building, secured an increase from 2.4 to 4 MVA, giving two 4 MVA supplies with N-1 resilience.
  • Progressed a separate, longer-term application for a much larger connection.
Second building, same campus
EXISTINGSECURED BY US 4.02.44.04.0+1.6 ABAB BEFOREAFTER N-1: 2.4 MVAN-1: 4 MVA
Supply B raised from 2.4 to 4 MVA. Dashed lines show N-1 capacity: what the building keeps if either supply is lost.
Before2.4 MVALimited by the existing cable run
After4 MVACable run uprated
Resilience2 × 4 MVAN-1, not possible before
Reading the capacity correctly

27 MVA is the combined import capacity of two separate, non-firm supplies. It is not IT load, and it is not 27 MVA from either supply. The supplies must not run in parallel, and if an 11 kV circuit is lost, on-site generation carries that side. That is why the supply strategy and the site’s electrical design have to be set together.

Project experience of Mousa Consultancy’s director, acting directly for the client. Client name and DNO references withheld.